Schedule

Monday 4/18
Have the sensor module prototype ready for possible installation

Thursday 4/21
Have a physical look and feel prototype ready for the personal in home unit

Monday 4/25
Have the pysical system running for user testing. 
If sensor is not installed work out test data for the system.
Possible presentation at the Beacon institute this evening??

Thursday 4/28
Work on the Web site to display the data and connect users to api
Rough working draft of paper (Compile prior art and resources

Monday 5/2
Compile data about sewer shed area and create maps

Thursday 5/5
Final user testing of the prototypes and web services
Rough draft of paper

Monday 5/9
Have a demo of the final system running with pysical and web interaction

Monday 5/13
Finish PAPER!!